In Lviv, engineering networks are 90% installed on the stretch from Yunakiva Street to Yatskova Street

On the street Shevchenko, repair work is ongoing on the section from the street. Yunakiv to st. Yatskova As LKP “Lvivavtodor” reported, repair work on this area is planned to be completed by the end of the summer, if the war does not make its corrections. As of now, 90% of all engineering networks have been installed here.

“From June 16, the contractor started work on the site from the street. Yunakiv to st. Yatskova On this section, 90% of the work on the construction of engineering networks and 5% of the work on the construction of the carriageway and tram track have already been completed.

I would like to note that the cost of works has not changed, despite the fact that we have a significant increase in prices. The contractor is working in accordance with the approved estimate,” said Mykola Vlasyuk, director of the Lvivavtodor LLP.

certificate
According to Lvivavtodor LLP, on the street Shevchenko, on the plot from St. Yunakiv to st. Yatskova, the following construction works were performed:

We will remind you that the III stage of the reconstruction of St. Shevchenko started on June 1 last year. It is about the plot from the street. Zaliznychna to st. Yaroslav the Wise, a little more than 1 km long.

The reconstruction project of St. Shevchenko provides for the complete dismantling of road surfaces, tram tracks and sidewalks, the cutting of green spaces that fall within the limits of the works, the reconstruction of all engineering networks. Arrangement of the carriageway and the new tram tracks combined with it in the middle of the street, arrangement along the carriageway on both sides of the bicycle lanes, arrangement of pockets for emergency services vehicles and temporary parking for the cars of residents of nearby buildings. Arrangement of sidewalks and pedestrian areas with provision of comfortable conditions for movement and recreation of groups of the population with reduced mobility. Arrangement of contact network of the tram, street lighting, improvement of the street space.