Major renovation in Sheptytsky People’s House continues

In October, a major renovation began in Sheptytsky People’s House aimed at strengthening the load-bearing and enclosing structures.

Currently, specialists from the contracting organization have drilled 132 holes 3 meters deep and 24 holes 6 meters deep. Special pipes have been installed in them, through which a special solution is delivered under high pressure. This solution fills the cavities and strengthens the foundation.

In 2018, during an inspection of the building, cracks in the foundation were discovered. Since then, a series of technical examinations have been conducted, indicating the need for reinforcement.

The works are being carried out by the contracting organization LLC “Expert System”, which won the tender. The cost of the work is 4,092,000 UAH.