LMKP “Lvivteploenergo” is preparing for the new heating season. Yes, on the street Stryiska is undergoing replacement of the main heat network from CHP-1. According to the heating engineers, this is a large-diameter network that has been in operation since 1981, so it has expired.
“According to the enterprise’s investment program, we started replacing the main heating network on the street. Stryyska. Here, 130 m of pipeline with a diameter of 720/900 mm will be replaced. This is a large-diameter network, and it branches off into several nearby streets. Therefore, its replacement is very important for reliable operation in the winter period.
We change the pipes to pre-insulated ones. This will reduce heat loss, and also increase the reliability of such a pipe.
It should be noted that these works were started at the time of hydraulics, in order to reduce inconvenience due to the lack of hot water. After all, the work to replace the heating network also requires the suspension of hot water supply,” Lvivteploenergo LMKP reported.
We will remind you that since May 1, Lviv heat supply companies have started hydraulic tests of heat networks. As Iryna Marunyak, deputy mayor of Lviv for housing and communal services, emphasizes, high-quality hydraulics allows you to quickly enter the heating season and quickly supply heat to the apartment.