Connection Rates to Lvivoblenergo Power Grids for 2025

The rates for standard connections to the power grids of PJSC “Lvivoblenergo” for 2025 have been approved by the NEURC Resolution No. 2119 dated December 18, 2024. These rates are now available on the company’s official website.

Additionally, rates for non-standard connections and the linear part of the connection have been published, approved by NEURC Resolution No. 2120 of the same date.

✅ The new rates will take effect on January 1, 2025.

Criteria for Standard and Non-Standard Connections

  • Standard connection includes connecting to the grid within 300 meters and a capacity of up to 50 kW.
  • Non-standard connection applies to cases that do not meet the criteria for standard connections, as well as connections for temporary structures.

How to Apply for Connection?
You can submit documents for connection or capacity increase through the following options:

  • Remotely via the Personal Account for Technical Conditions Applications.
  • In person at the Customer Service Center.

📌 For detailed information on connection steps and required documents, visit:
Steps and Documents for Connection.

📊 Find out the costs: