Economy

Control Process withdraws claim from Paris arbitration over Lviv waste processing plant

Polish company Control Process S.A., the former contractor for the construction of the waste processing plant in Lviv, has withdrawn its claim from the International Court of Arbitration of the International Chamber of Commerce (ICC) in Paris and requested that the arbitration proceedings be terminated. This was reported by LKP “Zelene Misto” (Green City).

The matter concerns a claim filed on 5 March 2026. The municipal enterprise notes that from the outset of the process it defended its position and challenged the ICC’s jurisdiction in this case. The arbitration did not proceed to consider the issue of the court’s powers, did not hold hearings and did not issue any decisions on the substance of the dispute.

Previously, the emergency arbitrator appointed at the request of Control Process itself had fully rejected the company’s demands to prohibit LKP “Zelene Misto” from completing the plant with other contractors. The arbitrator also ordered Control Process to reimburse 12 thousand euros in legal costs; however, according to the enterprise, this amount has still not been paid.

“There were so many loud statements, threats and claims that Lviv had supposedly lost all the arbitrations. And now the former contractor of the waste processing plant, the Polish company Control Process, has itself withdrawn its claim from the arbitration in Paris. Without any explanation… But what we do know for certain is that there is no arbitration decision on the substance of the dispute that would confirm the contractor’s loud claims about Lviv’s defeat. The city will continue to defend its interests and seek reimbursement of its costs,” — Andriy Sadovyi

LKP “Zelene Misto” emphasises that Control Process has not explained the reasons for withdrawing the claim. The enterprise considers this to be yet another change in the company’s tactics, which throughout the process repeatedly resorted to delaying the consideration of the dispute.

According to LKP, Control Process S.A., selected in an EBRD tender, never demonstrated during the implementation of the project that it was capable of properly fulfilling its contractual obligations, but instead actively engaged legal advisers to handle disputes. The enterprise suggests that the company may be looking for new ways to avoid liability.

“Zelene Misto” does not object to the termination of the arbitration proceedings in connection with the withdrawal of Control Process’s claim. The municipal enterprise plans to seek to have all arbitration-related costs imposed on the Polish company, as well as to pursue reimbursement of legal expenses.

LKP recalls that Control Process had previously publicly claimed that Lviv had allegedly lost all arbitration disputes concerning the construction of the waste processing complex. At the same time, the enterprise has consistently stressed that there are no arbitration decisions on the substance of the dispute that would confirm such claims.