Today, December 17, planned repair works are ongoing on the Hirne – Drohobych main water pipeline. The teams of KP “Drohobychvodokanal” are actively engaged in fixing leaks in hard-to-reach areas of the settlements of Stebnyk, Ulychne, and Hirne. The most significant tasks are being executed at the second lift pumping station in Hirne, where replacement of shut-off valve equipment is taking place.
An important mechanism regulates the water supply process. In parallel, energy technicians are inspecting line disconnectors near the wells. Another team is reviewing the starting equipment of pumping units at the same station. A total of 43 workers and 14 units of special equipment are involved in the operations.
Once all production tasks are completed, the process of restoring water supply will commence.