City demands €3.6 million for contract breach

Due to the failure to meet the contract terms for the construction of the plant, the city has called for the payment of €3.6 million in bank guarantees.

Because of the contractor’s refusal to carry out part of the work and the exclusion of a specific contractor from the site, as well as the non-supply of equipment and incomplete project work, LKP ‘Green City’ has approached the Polish bank-guarantor. The plant was supposed to be completed by October 4, 2025, but the facility is still not ready: the main building is unfinished, infrastructural networks and some of the works have not yet started.

**The Polish company Control Process** claimed delays due to air alerts. However, emergency services reported that their total duration was only two days. “The bank guarantee is unconditional and irrevocable,” explained LKP ‘Green City’.

Пов'язані статті

The city council emphasizes the importance of completing the plant to address waste management issues in Lviv. At the same time, the city must respond to contract violations.