The Commercial Court has upheld the claim of the Drohobych District Prosecutor’s Office and ordered a contracting organisation to pay more than UAH 5.4 million in penalties for failing to comply with the terms of a road repair contract in Stebnyk.
It was established that in May 2023 the Department of Municipal Economy of Drohobych City Council concluded an agreement with a company specialising in the construction of roads and motorways. The contractor was to carry out major repairs to the road on one of Stebnyk’s streets, with the value of the works amounting to almost UAH 11 million.
However, within the period stipulated by the agreement, the company did not commence the repair works. The terms of the contract provided for a penalty of 50% of its value, i.e. more than UAH 5.4 million, but the client failed to take action to recover this amount from the contractor.
In response to the violation, prosecutors filed a claim with the court seeking recovery of the contractual penalties. The Commercial Court agreed with the arguments presented and upheld the claim in full.
Once the court’s decision becomes final, the Drohobych District Prosecutor’s Office plans to take measures to enforce it compulsorily.