Влада працює

Reconstruction of the side section of the street. B. Khmelnytskyi near AC-2 ends

As LKP “Lvivavtodor” reported, the reconstruction of the side section of the street. B. Khmelnytskyi, near AS-2, namely from building No. 223v to building No. 223, is being completed. Yesterday, the contracting organization “Onur” LLC laid the bottom layer of asphalt on the roadway, and today they completed the installation of hatches and rain-receiving gratings at the level of the final layer of asphalt. Therefore, in the near future, under favorable weather conditions, they will start laying the top layer of the coating.

“As of now on the street B. Khmelnytskyi, from building No. 223b to building No. 223, the old pavement was dismantled, high-voltage power cables were replaced, a collector for rainwater drainage was laid, curbs and curbs were installed, sidewalks were arranged, a trough was also arranged for the road base of the carriageway and structural layers and the bottom layer of asphalt is laid.

It remains to lay the top layer of the coating, arrange the adjacency of the entrance area to the warehouse premises to the street. B. Khmelnytskyi, to sow lawns and complete the improvement of the territory”, – said LKP “Lvivavtodor”.

We will remind, as part of the reconstruction of the street B. Khmelnytskyi’s contracting organization “Onur” LLP, on the order of “Lvivavtodor” LLP, arranges a side entrance to the warehouse from the street. B. Khmelnytskyi, from building No. 223v to building No. 223. The total length of this section is about 130 m. Work on this section started on April 11.

Голос Сокальщини на GoogleNews