In the Chervonohrad community, road repair work is ongoing

In the rural areas, as noted by the first deputy mayor Dmytro Balko, work on road filling with crushed stone was completed at 24 facilities in the amount of 2,124,000 hryvnias.

Asphalting works on four roads have been completed. Three of them, in the amount of UAH 180,000, have already been paid. One payment for UAH 831,000 was submitted to the treasury for payment. The executor of the works is “Soris” PE.

Road repairs are underway along the street. Lvivska, B. Khmelnytsky and Krushelnytska. Work will soon begin on the street. Krystynopilska. Subcontractors are “Shlyahovyk – T” LLC and “Welt Capital” LLC. In Sosnivka, road repair is being carried out by the “Roma” PE.

For three objects, KP “Komunalnyk” terminated the agreements due to the fact that the executor planned to complete them by the end of the summer. According to the tender documents, the deadline for the completion of the works was at the end of May. Therefore, a tender has been announced for these roads (Sokalska Street, Bichna Promyslova Street and Myru Street in the village of Boryatyn). Procurement procedures are currently ongoing. Road repairs are planned to be completed by the end of June.

According to Dmytro Balk, the only settlement where a tender was not held is the town of Hirnyk. It will be announced after the KP “Chervonohradzhitlokomunservice” has worked out the technical task.