War is not an obstacle: what reconstructions and overhauls were carried out on the streets of Lviv in 2022

Wherever the enemy steps on our holy land with a dirty boot, there is devastation and grief. Whole cities and villages turn into ruins, life into death. This is the struggle of light against darkness – the nation of builders against destroyers. And victory in this fierce battle is ours! After all, despite the “barrage” of missile attacks and constant blackouts, Ukrainians continue to live, work and build their country. We look to the future. To a future in which there will no longer be a Russian Federation.

This year has been hyper-difficult for all of us. The LKP “Lvivavtodor” team had many ambitious plans for 2022, but the war put many of them “on pause”. Despite the extremely difficult conditions of wartime, it was possible to continue some of the important infrastructure projects for the city in the field of reconstruction, capital repair of streets, the customer of which is the company. – they inform the Voice of Sokal Region at the “Lvivavtodor” LKP

Actually, when martial law was introduced in Ukraine, contractors one by one began to announce the onset of force majeure and the suspension of work on all facilities where Lvivavtodor LLP is the customer. In the summer, it was gradually possible to “thaw” and activate part of these works. Here are the results for 2022!

P. Orlyk Street has become completely pedestrianized

The main works on the reconstruction of St. P. Orlyk is actually completed. Repairs were carried out in parts, accordingly, traffic was opened in stages. In particular, on November 16, the last section – from the street Mazepy to building No. 2 on the street. P. Orlyk.

In general, as part of the reconstruction of St. P. Orlyka, almost 1 km of new road surface was made, all communications were replaced, parking pockets for 98 cars were arranged, 46 trees were planted, etc. Near the children’s hospital, parking for 62 cars and a serpentine “path” for people with disabilities should be arranged.

 

On the street Pekarska became a new public space

As part of the capital repair of St. Pekarska this year marked the road and arranged a public space. A new recreation area has appeared on the site of the dismantled MAF near the Lviv National University of Veterinary Medicine and Biotechnology named after S. Z. Gzhitskyi. 5 benches were installed, an area of 119 square meters was paved with tiles. m. and landscaping was carried out. In the summer, it is especially pleasant to sit in the shade of the trees and admire the reconstructed street. Pekarska.

 

As part of the reconstruction of St. Asphalting of the last two sections of Shevchenko has begun

Shevchenko Street is one of the largest road arteries of the city and connects traffic flows from different directions. Therefore, the continuation of work on this object was a priority. Already in May, it was possible to restore the last stage of the reconstruction of the street. Shevchenko.

What do we have as of today? The section from the street was opened for traffic. Zaliznychna to st. Yatskova, at the same time the intersection of St. Shevchenko – str. Yatskova still remains closed. Currently, work is being carried out on the last two sections – from the street Yatskov to St. Bortnyanskyi and from St. Bortnyanskyi to st. Yaroslav the Wise. Actually, on December 24, the contractor began laying the bottom layer of asphalt concrete on both of these sections of the street. Along the entire length of the carriageway from the street. Yatskov to St. Bortnyanskyi, the bottom layer of asphalt concrete was completely laid (length – 235 m), from the street Bortnyanskyi to st. Yaroslav the Wise, the bottom layer was laid on a 70 m long section.

 

Reconstruction of the street Bandera: dismantling of the emergency retaining wall, arrangement of the transport hub

On the street This year, Bandera partially applied road markings, in particular at the intersection with the street. Antonovych and St. Rusovyh, the first adjustable diagonal pedestrian crossing in Lviv became operational.

 

As part of the reconstruction of St. Bandera launched the following traffic light objects:

St. Bandery – st. Polytechnic;
St. Bandery – st. Antonovycha – st. Rusovyh (with additional arrangement of a diagonal pedestrian crossing across Bandera St., Rusovyh St. and Antonovycha St.);
St. Bandery – st. Heroes of the UPA;
St. Bandery – st. Fedkovych.

Also this year, the emergency retaining wall near the Organ Hall was dismantled and a new one was installed in its place (a “green slope” will be made on top of it). Actually, on December 19, the traffic lane along this retaining wall, which was closed for almost 4 months due to the above-mentioned works, was opened for traffic. In addition, in the fall, work began on the construction of a transport hub at the intersection of St. Bandery – st. Chuprinka

 

On the street The farm was equipped with turning points for large-sized transport

As part of the reconstruction of St. Farmhouse in the area of St. Demnyansk made two U-turns for more comfortable passage of large vehicles. To complete the reconstruction, it remains to build the stairs to the Sykhiv bridge, as well as to plant green spaces, in particular, the project provides for the planting of about 450 trees.

 

On the street B. Khmelnytskyi, new benches and bicycle parking spaces were installed

As part of the reconstruction of St. B. Khmelnytskyi on the plot from St. Promyslova to st. 8 benches, 28 bicycle parking spaces, 6 bicycle racks and 14 garbage cans were installed in Lypinsky this year